March 12, 2026
Building Permit Processing Time: How Long Does Approval Take?
How long does a building permit take in Germany? Processing times by procedure, federal state, and project type – including tips to speed things up.
Introduction
You have submitted the building permit application (Bauantrag) – but how long do you have to wait for the approval? The processing time varies by federal state, procedure, and project type. Here you will learn what timelines to expect and how you can speed up the process.
Processing Times at a Glance
By Type of Procedure
|
| Simplified approval procedure | 4–8 weeks |
| Standard approval procedure | 8–16 weeks |
| Building permit with environmental review | 12–24 weeks |
| Preliminary building inquiry | 2–6 weeks |
By Federal State
|
| Bavaria | 6–10 weeks |
| Berlin | 8–16 weeks |
| Hamburg | 8–12 weeks |
| NRW | 6–12 weeks |
| Saxony | 6–10 weeks |
| Baden-Wuerttemberg | 6–12 weeks |
Note: These timelines apply to complete applications without supplementary requests. Incomplete applications take significantly longer.
What Affects the Processing Time?
Factors That Speed Things Up
|
| Complete documents | No supplementary requests = faster |
| Simplified procedure | Fewer review points |
| Pre-obtained neighbor consent | No consultation process needed |
| Existing local development plan | Clear guidelines |
| Digital building application | Faster processing |
Factors That Cause Delays
|
| Missing documents | +2–6 weeks |
| Neighbor objection | +4–12 weeks |
| No local development plan (Section 34 BauGB) | +2–4 weeks |
| Heritage authority consultation | +4–8 weeks |
| Environmental review | +8–16 weeks |
| Overloaded authority | +2–8 weeks |
How Long Is a Building Permit Valid?
|
| Berlin | 3 years | Possible, 1 year |
| Bavaria | 4 years | Possible |
| NRW | 3 years | Possible, 1 year |
| Hamburg | 3 years | Possible |
| Saxony | 3 years | Possible |
Important: You must begin construction within the validity period. You do not necessarily have to complete it, but construction must show recognizable progress.
Applying for an Extension
- Before the validity period expires
- At the building regulatory authority (informal application)
- Cost: 50–200 EUR
- Requirement: No change in the legal situation
When Am I Allowed to Start Building?
After Receiving the Approval Notice
You may build as soon as you have received the approval notice (Genehmigungsbescheid). However:
- Notify the authority of construction start: Report to the building regulatory authority before the first ground is broken
- Observe the objection period: Neighbors have 1 month to file an objection. You may still build, but at your own risk.
- Fulfill conditions: Check the approval notice for conditions that must be met before construction begins.
In Case of Deemed Approval (Genehmigungsfiktion)
In some federal states, the application is deemed approved if the authority does not respond within a statutory deadline. Requirements:
- Simplified procedure
- Complete documents
- Deadline expired (depending on the state: 1–3 months)
Tips to Speed Up the Process
Before Submitting the Application
- Submit a preliminary building inquiry: Clarifies fundamental questions in advance
- Involve neighbors: Obtain consent in advance (avoids the consultation process)
- Review the local development plan: Does the project comply with the B-Plan? Deviations = delays
When Submitting the Application
- Complete documents: Every supplementary request costs 2–6 weeks
- Digital building application: Submit online where possible
- Choose an experienced architect: One who knows the local authority and its requirements
After Submitting the Application
- Follow up: After 6 weeks, politely inquire about the status
- Respond quickly to supplementary requests: Every day counts
Frequently Asked Questions
Can I start building before the permit is issued?
No. Building without a permit constitutes unauthorized construction (Schwarzbau) and can result in a demolition order. Exception: In extreme cases, a provisional building permit (partial permit) can be applied for.
My application has been pending for 4 months – what can I do?
Inquire in writing about the processing status. Set a reasonable deadline (2 weeks). If the authority remains inactive, you can file an action for failure to act (Untaetigkeitsklage) at the administrative court.
Does a renovation take as long as a new build?
Often shorter. Renovations and changes of use are frequently processed under the simplified procedure. However, complex renovations (listed building protection, structural issues) can take longer.
Does the digital building application really shorten the processing time?
Yes, generally. Internal processing becomes more efficient. In Berlin, the digital building application has noticeably shortened processing times.
Summary
- Simplified procedure: 4–8 weeks
- Standard procedure: 8–16 weeks
- Biggest time waster: Incomplete documents
- Validity period: 3–4 years (extendable)
- Tip: Submit complete documents + digital + experienced architect
- Build only after approval – do not risk unauthorized construction
Related Tips
Sources
Last updated: 29. Januar 2026