Skip to content

March 12, 2026

Building Permit Processing Time: How Long Does Approval Take?

How long does a building permit take in Germany? Processing times by procedure, federal state, and project type – including tips to speed things up.

Introduction

You have submitted the building permit application (Bauantrag) – but how long do you have to wait for the approval? The processing time varies by federal state, procedure, and project type. Here you will learn what timelines to expect and how you can speed up the process.

Processing Times at a Glance

By Type of Procedure

ProcedureTypical Duration
Simplified approval procedure4–8 weeks
Standard approval procedure8–16 weeks
Building permit with environmental review12–24 weeks
Preliminary building inquiry2–6 weeks

By Federal State

Federal StateAverage Duration
Bavaria6–10 weeks
Berlin8–16 weeks
Hamburg8–12 weeks
NRW6–12 weeks
Saxony6–10 weeks
Baden-Wuerttemberg6–12 weeks
Note: These timelines apply to complete applications without supplementary requests. Incomplete applications take significantly longer.

What Affects the Processing Time?

Factors That Speed Things Up

FactorEffect
Complete documentsNo supplementary requests = faster
Simplified procedureFewer review points
Pre-obtained neighbor consentNo consultation process needed
Existing local development planClear guidelines
Digital building applicationFaster processing

Factors That Cause Delays

FactorTypical Delay
Missing documents+2–6 weeks
Neighbor objection+4–12 weeks
No local development plan (Section 34 BauGB)+2–4 weeks
Heritage authority consultation+4–8 weeks
Environmental review+8–16 weeks
Overloaded authority+2–8 weeks

How Long Is a Building Permit Valid?

Federal StateValidity PeriodExtension
Berlin3 yearsPossible, 1 year
Bavaria4 yearsPossible
NRW3 yearsPossible, 1 year
Hamburg3 yearsPossible
Saxony3 yearsPossible
Important: You must begin construction within the validity period. You do not necessarily have to complete it, but construction must show recognizable progress.

Applying for an Extension

  • Before the validity period expires
  • At the building regulatory authority (informal application)
  • Cost: 50–200 EUR
  • Requirement: No change in the legal situation

When Am I Allowed to Start Building?

After Receiving the Approval Notice

You may build as soon as you have received the approval notice (Genehmigungsbescheid). However:

  1. Notify the authority of construction start: Report to the building regulatory authority before the first ground is broken
  2. Observe the objection period: Neighbors have 1 month to file an objection. You may still build, but at your own risk.
  3. Fulfill conditions: Check the approval notice for conditions that must be met before construction begins.

In Case of Deemed Approval (Genehmigungsfiktion)

In some federal states, the application is deemed approved if the authority does not respond within a statutory deadline. Requirements:

  • Simplified procedure
  • Complete documents
  • Deadline expired (depending on the state: 1–3 months)

Tips to Speed Up the Process

Before Submitting the Application

  • Submit a preliminary building inquiry: Clarifies fundamental questions in advance
  • Involve neighbors: Obtain consent in advance (avoids the consultation process)
  • Review the local development plan: Does the project comply with the B-Plan? Deviations = delays

When Submitting the Application

  • Complete documents: Every supplementary request costs 2–6 weeks
  • Digital building application: Submit online where possible
  • Choose an experienced architect: One who knows the local authority and its requirements

After Submitting the Application

  • Follow up: After 6 weeks, politely inquire about the status
  • Respond quickly to supplementary requests: Every day counts

Frequently Asked Questions

Can I start building before the permit is issued?

No. Building without a permit constitutes unauthorized construction (Schwarzbau) and can result in a demolition order. Exception: In extreme cases, a provisional building permit (partial permit) can be applied for.

My application has been pending for 4 months – what can I do?

Inquire in writing about the processing status. Set a reasonable deadline (2 weeks). If the authority remains inactive, you can file an action for failure to act (Untaetigkeitsklage) at the administrative court.

Does a renovation take as long as a new build?

Often shorter. Renovations and changes of use are frequently processed under the simplified procedure. However, complex renovations (listed building protection, structural issues) can take longer.

Does the digital building application really shorten the processing time?

Yes, generally. Internal processing becomes more efficient. In Berlin, the digital building application has noticeably shortened processing times.

Summary

  • Simplified procedure: 4–8 weeks
  • Standard procedure: 8–16 weeks
  • Biggest time waster: Incomplete documents
  • Validity period: 3–4 years (extendable)
  • Tip: Submit complete documents + digital + experienced architect
  • Build only after approval – do not risk unauthorized construction

Related Tips

Sources

Last updated: 29. Januar 2026